Hamms Landfill Solar Farm

Project Scope:

  • 3,250 LF of Demolition of Existing Piping
  • 25,000 SF of Access Road and Laydown Area
  • 1,564 Leveling & Installation of Ballast Blocks
  • 1 Complete Solar Panel Racking System
  • 2,000 CY of Imported & Placed NJDEP Certified Topsoil
  • 13 Acres of Restoration

Project Summary:

Site and mechanical scope package for Hamms Solar Farm.  Install SWPPP perimeter controls, access road and staging area.  Intermittently grade site to conform site to solar system equipment tolerances.  Place, level and compact stone leveling pads.  Set precast ballast.  Construct solar array racking system.  Maintain and stabilize site.