Changewater Solar Farm

Project Scope:

  • 7,200 LF of Electrical and Communication Duct Bank Excavation & Backfill
  • 2,900 LF of Directional Drilling
  • 21 Electrical Precast Manholes
  • 1 Switchgear Pad
  • 10,100 LF of Restoration

Project Summary:

Electrical and communication duct bank civil support including excavation, sand bedding, select backfill of trenches.  Furnish and install 21 precast electrical/comm manholes.  Horizontal directional drill through environmentally sensitive easements which included a challenging rock drill through ledge rock.