Project Scope:
- 45 Acres of Site Clearing & Grubbing
- 20,800 LF of Silt Sock Installation
- 24,000 LF of Construction Fence Installation
- 12,500 CY of Earthwork
- 250 LF of Culvert Installation
- 7,070 LF of Flow Diffuser
- 31,600 SF of Temporary Access Roads
- 31,600 SF of Permanent Roads
- 27,000 SF of Laydown Areas
- 50 Acres of Stabilization & Seeding
Project Summary:
The Ticonderoga Solar project involves large-scale civil site development to prepare the site for solar installation, including extensive grading, roadway construction, and installation of drainage and stormwater infrastructure. Work also includes implementation of erosion control systems and ongoing site stabilization to maintain compliance throughout construction.
The scope is executed under a coordinated construction approach with the client, emphasizing schedule adherence, site logistics, and efficient sequencing to support overall project delivery.